bob and alice can finish a job together in 3 hours . if bob can do the job by himself in 5 hours , what percent of the job does alice do ?
1. 20%
2.30%
3.40%
4.50 %
5.60 %
kaplan word problem
This topic has expert replies
- pradeepkaushal9518
- Legendary Member
- Posts: 1309
- Joined: Wed Mar 17, 2010 11:41 pm
- Thanked: 33 times
- Followed by:5 members
- tpr-becky
- GMAT Instructor
- Posts: 509
- Joined: Wed Apr 21, 2010 1:08 pm
- Location: Irvine, CA
- Thanked: 199 times
- Followed by:85 members
- GMAT Score:750
If Bob does the job alone in 5 hours then his rate is 1/5 per hour - in three hours he does 3/5 of the job leaving Alice with 2/5 of the job to do which is equal to 40%.